Major Fire Dept issues rise in March City Council

News

JASPER, Ga. – Several issues have mounted up on the Jasper Fire Department in the last month.

The issues are also mounting into a major budget issue for the city as they seek repair Fire Engine #2 from engine troubles and deal with an unbudgeted Fire Interface Purchase. Both of the issues come amid a new vehicle purchase for the Fire Department as well.

While the Council did agree that the engine repairs could be covered as Chief Steve Roper suggested he had a few projects that he could put off until next year in order to pay for the major issue of the repair, including a driveway repair and a painting project.

As the Fire Engine requires an “in-frame repair” as Roper called it, the need could cost nearly $30,000 if the engine block needs to be fully rebuilt. However, Roper also said there is a chance the issue could be a smaller issue needing a gasket replacement costing $7,500.

The council approved up to $30,000 for the repairs to come from the line items of the other projects.

However, this was not the biggest issue the Fire Department saw as the next item on the agenda listed a 911 Interface Purchase.

Roper informed the council that the department has been in process of establishing a Computer Assisted Dispatch interface since 2018 and has seen stalls throughout last fall and winter. This system was picked up again this year with a total cost of $18,120.

The interface, according to Roper, will allow all information that 911 has taken into the system and dumps the information into Ipads for users to instantly access the information, history, and conditions among other things. This not only accumulates and accesses this information, but cuts down on radio traffic and aids in reporting for the city as well.

However, the $15,120 has been spent to proceed with this project, but was not budgeted in the 2019 budget. Jasper City Councilmember Anne Sneve clarified in the meeting that it was budgeted at one point but postponed. Having never returned to the budget, the City is now facing the $18,120 unbudgeted expense and seeking a way to cover the cost.

Roper said that he had a conversation with the City Manager, Jim Looney at the time, earlier this year about the project and its importance to the city overall. He said, “He gave me the go ahead to proceed with the project, and that’s where I am right now.”

While Jasper City Councilmember Tony Fountain noted that if the engine issue comes in to cost $7,500, they could could use the remaining funds to cover the $18,120 for the interface system, he also questioned what the city would do to respond if the engine took the entire $30,000.

Mayor John Weaver offered his opinion saying, “I think we need to give a stern reprimand that we did not know that we had approval for a $18,120 item before this council.”

Jim Looney was present at the meeting and took responsibility for the mistake as he said his understanding was that it was budgeted, but has now discovered it was not.

As the council moves forward, they are still seeking funds to cover the expense in case the engine repairs monopolized the excess funds from the canceled Fire Department projects.